Guilan Combined Cycle Power Plant (1350 M.W. CCPP)

This project consisted of gas and steam divisions, executed under the supervision of Siemense Co. by Balagar Company.
The work operations comprised:

Concreting 160,000 m3
Reinforcing 10,000 tons
Formwork 170,000 m2
Steel Structure 6,000 tons
Excavation 550,000m3
Filling & Embankment 500,000 m3
Installation of Embedded Parts 280 tons

Client: Tavanir Co.

Tavanir Central Laboratories And Repair Shops

This project consisted of the following sections:

1)Inspection Building, 2)Guest House, 3)Administrative Building, 4)Fire_Fighting, 5)Motorpool Building, 6)Canteen, 7)Transformers Maintenance Workshop, 8)Workshop for All Types of Machinery & Equipment, 9)Mechanecal Laboraty, 10)Metal Industry Workshop, 11)General Workshop, 12)Galvanization And Bearing Production Workshops, 13)Quenching Laboratory, 14)Melting and Casting Of metal Workshop, 15)Model Preparation workshop, 16)Storage, 17)Personel Attendance Building, 18)Health & Laboratory Complex, 19)Storage for Electrical Equipment, 20)Water Tank, 21)63 KV substation, 22)R.C. underground Ducts,

Client: Tavanir Co.

Bandar Abbas 63/20 K.V. Substation Refinery Residential Complex

This project consisted of :
Control Building 500 m2
Total substation area 6000m2
Foundation & cable trenches

Client: National Iranian Oil Company (N.I.O.C)

See Appreciation: (1)

South Pars Gas Refinery Field Development – Phase 1 (Utility Facilities)

This project consist of following sections
BUILDINGS:
Substation(no 1, 2, 3, 4), Main switch room, Utility Control Room, Lokal Equipment Room.
GENERAL CIVIL WORK
Pipe Supports , Pipe Sleepers , Pipe Racks , Paving , Roads , Temporary Foundations , Platform , Shelters , Drainage System , Underground Piping , Cable Trench , Manhole and Value pit
DESALINATION PACKAGE , FIRE WATER SYSTEM , PLANT WATER SYSTEM , CHEMICAL SYSTEM , POTABLE WATER SYSTEM , DEMINERALIZED WATER SYSTEM , STORAGE TANK , PLANT WATER TANK , POTABLE WATER ST.TANKS , DEMINE.WATER ST.TANKS(Boiler 1,2,3)

GAS TURBINE GENERATORS(1,2,3,4)
NITROGEN STORAGE VESSELS (1,2,3,4,5,6)
Nitrogen (N2) , Instrument / Plant Air System , Instrument Air Receivers , Inst./Plant Air Compressor , Wet Air Receiver , Diesel Oil Storage Tanks , Diesel Oil Dewatering Package
ELECTRICAL SYSTEM
Refinery Grounding , Area Lighting , Catodic Protection

Client: Mapna Co.

Assaluyeh Gas Power Plant (1000 M.W.)

This project included the execution of all civil and installation activities of Assalouyeh power plant which consists of a turbine hall and auxiliary units, control and switchgear buildings, transformers, fuel oil system, administration building, fire fighting, clinic and security buildings, guard house, and general civil works including plant access road, main and branch roads, guard towers, landscaping, protective fencing, flood control system, area cables, pipe trenches and much more.

Client: Mapna Co.